How long does a CGI campaign take, and what slows it down?
A CGI campaign usually takes two to three weeks for a small set of stills of one product, and four to seven weeks for a 30 to 60 second product film, based on what studios publish. Those numbers assume the brief is complete and feedback comes back on time. In practice, the schedule is set less by the computers than by two things the brand controls: how complete the product files are, and how quickly decisions get made.
How long do typical CGI projects take?
Published timelines are fairly consistent, as long as you compare like with like.
| Project | Published timeline | Source |
|---|---|---|
| One simple product, first draft of a render | 3 to 7 business days after the brief is approved | 360 Render |
| Complex product or lifestyle scene | 2 to 4 weeks, depending on workload and revisions | 360 Render |
| Stills only, one hero product, standard complexity | 2 to 3 weeks from brief to final delivery | XO3D |
| Hero product film, 30 to 60 seconds | 4 to 7 weeks, including pre-production, animation, render and grade | XO3D |
| CGI video in general | Most between two and six weeks | MadCGI |
Note what these figures measure. A first draft in a week is not a finished campaign. And none of them includes the weeks before the brief, when files are collected and NDAs are signed, or the time your own team needs to review.
A campaign for a luxury or beauty brand usually sits toward the upper end. Glass, liquid, metal and stones need more look development, and campaign work has more people approving than a catalog render.
Where does the time actually go?
Mostly into building the product and agreeing on how it looks. According to MadCGI, the model and the look development decide the schedule far more than the rendering does.
A typical campaign moves through these phases:
- Brief and concept. Agreeing on the idea, the shots and the formats. Short if the brief is clear, long if it is not.
- Modeling. Building the product in 3D from CAD, drawings or a sample. Fast with clean files, slow without them.
- Look development. Setting up materials and light so the glass, liquid, metal or cream looks right. This is where luxury products take the most time.
- Layout and animation. Placing cameras, building the set, timing the movement.
- Simulation, if needed. Liquid, splashes and texture swirls are calculated, and every change means calculating again.
- Rendering. Computers produce the final frames. For film this can take days, but it runs in the background.
- Compositing, grade and versions. Final color, any added elements, and all the formats and cut-downs.
Each phase ends with a review. That is where most calendars slip.
What slows a CGI project down?
Almost always the same handful of things, and most of them can be prevented in the brief.
- Missing product files. Without CAD, print-ready label artwork and finish references, the studio models from photos and waits for answers. Our guide on what to put in a brief for a CGI studio lists what to collect.
- A product that is still changing. A new cap or label halfway through means redoing work that was already approved.
- Feedback from many directions. Notes from five people in five channels have to be reconciled before anyone can act on them. 360 Render names a single approver as the change on the client side that does the most for the schedule.
- Late reviewers. A regional team or legal reviewer who first sees the work at the final stage can reopen decisions made weeks earlier.
- Reopening approved stages. 360 Render approves in stages, shape first, then materials and light, then final color, and does not revisit an approved stage. Going back costs the most time.
- Late changes to moving liquid. A new splash shape after the simulation is approved means simulating and rendering again. Our article on perfume bottles in CGI explains why liquid needs early sign-off.
- Formats added at the end. A 9:16 version is a new composition, not a crop. Asking for it in the final week adds days.
How much time should you plan for your own reviews?
More than most teams expect, and it belongs in the schedule from day one.
No studio we found publishes a standard for client review time. 360 Render says only that collecting all feedback before sending it back prevents delays. As a working assumption, not a published benchmark, plan two to three working days per review round for a small team, and more if legal, regulatory or regional teams need to see the work. For a campaign with four or five review moments, that alone can add two weeks.
Put the review dates in everyone’s calendar when the project starts, including the people who only sign off at the end.
Can a CGI campaign be rushed?
Partly. Some phases run in parallel, others cannot be compressed.
A studio can add artists, split shots between them, and rent extra render capacity. Stills and film can be built side by side from the same model. What cannot be rushed is agreeing on the idea and approving the look. Rush work also costs more, as our article on what a CGI beauty campaign costs explains.
There is a creative side to this too. Not Important Studio has written about deadlines as a balance: some pressure keeps work moving and forces decisions, but ideas also need time to settle before they are good. A schedule with no slack at all tends to produce the first idea, not the best one.
How do you build a realistic schedule?
Work backward from the date the files have to be live, and leave a buffer at every step.
- Live date. When does the campaign go out, in which channels?
- Delivery buffer. Leave time for uploading, trafficking and last checks by media teams. In our experience that is often a few days to a week.
- Final approval. Who signs off, and when are they available?
- Review rounds. Count each stage and give it review days.
- Production. Use the studio’s estimate for modeling, look development, animation and rendering.
- Brief locked. Product files, artwork, shot list and formats confirmed.
- Before the brief. NDA signed, files released by whoever owns them internally.
If the dates do not fit, cut scope before you cut review time. Fewer shots, fewer formats in the first wave, or a still instead of a moving-liquid shot will save more time than asking reviewers to decide faster.
How does this compare with photography?
For simple work, photography can be quicker. XO3D says a shoot can win on speed for a plain packshot, but that photography with built sets, retouching and several formats ends up taking about as long as CGI.
CGI gains time where photography has to wait: for a finished product, for a set to be built, or for a reshoot after a packaging change. Our comparison of CGI and photography for beauty campaigns goes through when each route makes sense.
Frequently asked questions
Is CGI faster than a photo shoot?
For a simple packshot of an existing product, a shoot is often quicker. Once you need custom sets, many formats or a product that does not exist yet, CGI timelines are comparable or shorter.
Can the studio start before the product design is final?
Yes, on the parts that are fixed. Tell the studio which parts may still change, so they plan those last and do not polish something that will be replaced.
Does adding a film to a set of stills double the schedule?
Not usually. The model, materials and lighting are shared, so the film adds animation, rendering and grading time rather than starting from zero.
What happens if our launch date moves forward?
Ask the studio what can run in parallel and what has to stay in sequence. Extra artists and more render capacity help, but they cannot shorten your own review time.